Project: 280 High Holborn

 



Architect : GMW Architects
Construction Manager : Mace
Project Value : £820,000
   
Scope of Works

Basement: WC walls and ceilings,Fire-stopping & Integrated Bulkheads

Ground Floor: Soffit Thermal linings, 3Dry-lining to all walls, SAS 330 Ceilings to Office areas, SAS 205 Ceilings to Corridors, SAS 130 Ceiling to Fire Control Room, Light Troughs and MF Ceilings to Reception & Baswaphon Ceiling to Reception

Levels 1 – 8: SAS 330 Ceilings Dry- Lining to all walls, Column Cladding, MF Ceilings, WCs MF Ceilings

Staircase: Dry-lining to all walls, Partitioning & MF Ceilings

   
Project Summary :

280 High Holborn was a CAT A Project with a fit out to the Reception and the WCs – Celtic worked closely with MEP (Mace’s M&E Managers) to ensure the integration of services into the SAS Ceilings worked prior to manufacturing.
Undertaking the 9 floors with the programmes overlapping made the planning Key to delivering this project not only on time but ensuring the quality wasn’t affected.